Applications should take six to eight weeks from the time they are registered complete. For major applications this period is 13 weeks. It is longer still if an Environmental Impact Assessment (EIA) is required. You can access more information on the planning process using these links:
Detailed desktop analysis
The case officer becomes familiar with the application and assesses issues that could be raised. The main parts of the planning application that are analysed are:
location of the development site
the site's relationship with neighbouring properties
constraints such as:
Tree Preservation Orders (TPOs)
conservation areas
flood zones etc
who has been consulted/notified
planning history of the site including:
planning conditions
reasons for previous refusals
application form details
ownership of the land
materials to be used
reports or statements made by the applicant
checks for accuracy of the plans
assessment of the plans
Site visit
Officers visit sites for most applications apart from Householder applications. For householder applications, it is for the case officer to decide if a site visit is necessary. The purpose of the site visit is to visualise the development in the context of its setting.
This part of the process is important. It helps officers understand the extent of the proposal on the site. Officers will note:
characteristics of the location including:
terrain
levels
surrounding buildings
the nature of the area
possible impacts on the neighbours including:
loss of light
overlooking
compatibility of uses
visual impacts including:
the effect on the street scene
fit with the existing character
access
appropriate siting
environmental impacts such as:
trees
hedgerows
flooding
local facilities
sustainability
Officers check that neighbours have been notified. The site visit is recorded using notes and photographs. Officers will note:
the date of visit
location of the site notice
any additional neighbours that have been notified.
The display of site notices is the responsibility of the case officer. We may sometimes ask applicants to put up the site notice.
Not all types of application need site notices.
Three week consultation
The application may be publicised using:
an advert in the local press
a site notice
letters to neighbours
consultations to the parish and other interested parties.
A minimum of 3 weeks is allowed for publicity. The case officer receives comments on the application during this time. These comments bring matters to their attention.
You can find more information on notification and publicity using this link: Notification and publicity for planning applications
Evaluation
This part of the process pulls all the information together to help make a decision. The case officer researches the wide-ranging source materials. This research can include:
histories of both the site and other similar cases
local and national planning policies
government guidance
case specific research
planning acts, regulations and case law
design guides
other supplementary planning documents
a further site visit if necessary for clarification.
The officer then:
gathers the information together and
considers it beside the information learnt at the start of the process.
This provides the basis for a balanced recommendation that is fundamentally supported by planning policy. In exceptional cases the recommendation may be weighted to the contrary by other material considerations.
A case officer may need to request:
further information from the applicant or
an amendment to the proposal.
The planning process should encourage good development. It is not a barrier. If an application is likely to be refused, our normal position is not to seek or accept amendments after validation. Options to avoid a refusal is to:
withdraw the application and
seek pre-application advice.
The decision
The officer's role is to:
investigate and assess the proposal's suitability and
communicate this in writing to the appropriate deciding body.
The majority of applications are decided by delegated powers. Major and more controversial applications are decided by Planning Committees.
Decisions can be:
approval
conditional approval
refusal
The officer or Planning Committee makes a decision. The applicant is notified by the decision notice. A conditional approval will have planning conditions.
Find out about discharging planning conditionsYou can find more information on the Council decides planning applications using the link below.
How planning applications are decidedYou can appeal against a refusal of planning permission. Find out more about appeals
Complaints process
If you are unhappy about how the Council has handled:
a planning application or
enforcement investigation
you can use our online complaint form. Our feedback team will aim to respond to you within 10 working days.
If your complaint is about your planning application decision, then you have the right to appeal. This is set out in your decision notice.
You can find more information on common planning complaints on our Common planning complaints page.
If you have complained and are unhappy with the response, you may refer the matter to the Local Government and Social Care Ombudsman (LGSCO).
Local Government and Social Care Ombudsman website
Please note:
The LGSCO cannot investigate a complaint just because you do not agree with the decision
They have no power to alter the decision.