Long Rock Strategic Coastal Improvements Project


Logo - text reads: European Union, European Regional Development Fund

The Long Rock Strategic Coastal Improvements Project was a £3.7m initiative. It aimed to improve resilience to flooding and coastal erosion. The benefits were targeted along the frontage of Mount's Bay. This frontage runs from Mount's Bay between Marazion and Eastern Green.

View the Long Rock Strategic Coastal Improvements Project infographic

Quick Look Summary

There were three distinct aspects to the project:

  • Coastal protection of the embankment. This embankment protects the railway line and properties behind it
  • Environmental improvements to Marazion Marsh
  • Improved fish and eel passage for streams entering Mount's Bay.

View the Long Rock Strategic Coastal Improvements quick look summary 

Funding

The project attracted:

  • £2.7 million from Defra's Flood Defence Grant in Aid (FDGiA) and
  • £1 million from the European Regional Development Fund (ERDF)

The latter was administered through DCLG (now MHCLG) under Priority Axis 5. This funding focussed on promoting climate change adaptation, risk prevention and management.

Timescale

The project ran from July 2017 through to December 2020. Note that the programme listed in the above infographic has been superseded.

Key Milestones

Action Date
Submission of Outline Application to DCLG December 2015
Submission of Detailed Application to DCLG June 2016
Receipt of conditional approval from DCLG September 2016
Submission of Outline Business Case to Defra September 2016
Receipt of approval from Defra June 2017
Review of costs and programme to ensure project deliverability June 2017
Initiation of Planning Performance Agreements June 2017
Resubmission to DCLG with revised programme July 2017
Pre-emptive project start date July 2017
Appointment of project controls August 2017
Receipt of approval from DCLG November 2017
Detailed design contract let January 2018
Commence surveys and ground investigations January 2018
Environmental surveys and all necessary permits obtained January 2018 - January 2019
Fish and eel pass detailed design completed November 2018
Sea defence works detailed design completed September 2018

Public exhibition on proposed works

Exhibition Summary Report

September 2018
Sea defence works planning application submitted September 2018
Marazion Marsh planning application submitted November 2018
Marazion Marsh detailed design completed March 2019
Sea defence works construction started March 2019
Sea defence works completed July 2019
Fish and eel pass works started August 2019
Fish and eel pass works completed October 2019
Marazion Marsh works started October 2019
Marazion Marsh works completed April 2020
Project evaluation November 2020
Project completion December 2020

 

Delivery Partners

  • Cornwall Council
  • The Environment Agency
  • Cornwall Development Company

Strategic Partners

  • Natural England
  • The RSPB
  • Network Rail

Delivery team

  • Client - Cornwall Council Environment Service
  • Project Commissioners - Cornwall Council Capital Projects Team
  • Project Managers - Ward Williams Associates
  • Contractor - Cormac Solutions Limited