Progress on the design and construction of the rest of the scheme can be summarised below.
Location |
Design |
Construction |
Perranporth to Goonhavern |
Detailed design complete |
Open |
St Agnes (Penwinnick Cottage to Park Kres) |
Detailed design complete |
Open |
St Agnes (Penwinnick Cottage) to Sevenmilestone |
Detailed design complete |
Open |
Sevenmilestone to Chiverton |
Detailed design complete |
Open |
Crossing of A30. Chiverton Bridge |
Detailed design Complete
|
Construction complete - opened April 2024 |
Chiverton to West Langarth |
Detailed design complete |
Construction complete |
PFA Research is an independent research company. They were appointed to undertake a summative assessment of the Saints Trails project. The objectives of the Summative Assessment are to:
- Show the progress, impacts and value for money of the project
- Check progress towards achieving the project’s ERDF outputs
- Check progress towards achieving the project’s impacts
- Identify, collate and summarise lessons learned. This will inform relevant future delivery and best practice for future projects
- Produce a final report consistent with the Programme Evaluation report summary template